Project Time Management:
This project was conducted during the period of one complete acedemic year at Central Washington University and roughly follow the schedule below
Fall Quarter:
-
Project Decision
-
Design and Analysis
-
Predictions of performance
-
Selection of Materials
Winter quarter:
-
Building device
-
Material purchases
-
Parts fabrication
-
Complete device assembly
Spring Quarter:
-
Testing
-
Documentation of device capabilities
-
Manufacturing Feasibility
Important dates:
-
Jan 12 – proposal review
-
Jan 31 - Completed proposal
-
Feb 5 – Critical Design Review
-
March 12 - Completed Prototype
-
March 26 – Function Analysis
-
May 25 – Testing Completion
-
June – Final Project Presentation
(Please note Appendix E for detailed gant chart and description of time spent on project)