Project Time Management:

This project was conducted during the period of one complete acedemic year at Central Washington University and roughly follow the schedule below

 

 

Fall Quarter:

  • Project Decision

  • Design and Analysis

  • Predictions of performance

  • Selection of Materials

Winter quarter:

  • Building device

  • Material purchases

  • Parts fabrication

  • Complete device assembly

Spring Quarter:

  • Testing

  • Documentation of device capabilities

  • Manufacturing Feasibility

Important dates:

  • Jan 12 – proposal review

  • Jan 31 - Completed proposal

  • Feb 5 – Critical Design Review

  • March 12 -  Completed Prototype

  • March 26 – Function Analysis

  • May 25 – Testing Completion

  • June – Final Project Presentation

(Please note Appendix E for detailed gant chart and description of time spent on project)